Wilmington, DE
In an ongoing effort to provide quality wireless service, AT&T has identified your community as one that will benefit from improved network coverage.
Milestone Towers is proposing a wireless telecommunications facility at The John Dickinson School, addressed 1801 Milltown Road Wilmington, DE 19808.
The proposal is for a 132-foot stealth tree pole and will include ground equipment required to operate the facility.
This equipment will be located at the base of the structure in a secure fenced area. AT&T will be the first wireless carrier to locate on the proposed tower.
Survey, FAA, FCC, NEPA, Phase 1, Geotechnical Analysis.
Site Plan Application, Special Use Permit Application, Community Notification, Board of Adjustments.
Conduct Bid Walk With Contractors and school representatives, submit site plan and building permit applications.
Tower construction = 4-6 weeks | Carrier construction = 4-6 weeks on average
On-site supervision by Construction Manager | Schedule with schools to minimize disturbance to student activities.
Four visits per year for site maintenance | Remove trash, debris, check signage.
Annual RF testing | 2-4 visits per year for carrier modifications.
With over 20 years experience, Milestone Towers is the leading developer of wireless infrastructure and cell towers in partnership with school, government and utility landowners.